Short answer: Off-plan homes sold by a developer to a consumer are "pre-paid housing sales" under Articles 40–46 of Consumer Protection Law No. 6502. The contract must be a title registration or a sale promise drawn up by a notary, no contract may be signed before the building permit, and delivery must take place within 48 months at the latest. You have 14 days to withdraw for free, and 24 months to withdraw with capped compensation of 2–8%. If the developer is late, you can insist on delivery and claim delay damages, or withdraw and claim a full refund; projects of 30 units or more must carry completion insurance or another guarantee.

Quick answers

  • Form: title registration or notarised sale promise; otherwise void, but the developer cannot rely on it against you.
  • Building permit: no contract, deposit or promissory note before it.
  • Delivery: at most 48 months from the contract (Regulation Art. 10).
  • Withdrawal: 14 days free; then up to 24 months with 2%, 4%, 6% or 8% compensation.
  • Guarantee: completion insurance or another guarantee for projects of 30+ units.
  • Delay: notice, then delivery plus damages, or withdrawal and refund.
  • Claims: arbitration committee below TRY 186,000 (2026); mandatory mediation before consumer court money claims.

Off-plan buying is attractive in Turkey: lower prices, staged payments and modern projects in Istanbul's Başakşehir and Esenyurt, Mersin, Antalya and Alanya. It is also where many foreign buyers lose money — through delays of years, unfinished buildings, developers in concordat, or units sold twice. Think of a Kuwaiti family that paid 60% of the price on a notarised promise in 2023, with delivery promised for 2026 and the building still at the fourth floor; or a Kazakh buyer in Mersin who signed a "reservation agreement" at a sales office. This guide by LimanLegal Law Firm, an Istanbul law firm, explains the protections and remedies as of 23 October 2026.

Key facts

Off-plan property in Turkey: the rules as of 23 October 2026
ItemRule
Legal basisConsumer Protection Law No. 6502 (Tüketicinin Korunması Hakkında Kanun), Art. 40–46; Pre-paid Housing Sales Regulation (2014, amended 2017 and 2022)
Who is protectedA buyer acting for private, non-commercial purposes, buying from a professional seller or developer
FormTitle registration at the land registry, or a sale promise drawn up by a notary
Building permitRequired before any contract; no deposit or promissory note before a valid contract
DeliveryAt most 48 months from the contract date
Free withdrawal14 days, no reason, no penalty; refund within 14 days
Withdrawal within 24 monthsCompensation capped at 2% / 4% / 6% / 8% of the price; refund within 180 days
GuaranteeBuilding completion insurance for 30+ units, or another guarantee
Project changesFree withdrawal within 1 month if the buyer does not accept the change
DisputesArbitration committee below TRY 186,000 (2026); consumer court above; mediation before money claims
LimitationGeneral limitation period of 10 years (Code of Obligations, Art. 146)

Which law protects off-plan buyers in Turkey?

Articles 40–46 of Law No. 6502 and the Pre-paid Housing Sales Regulation (Ön Ödemeli Konut Satışları Hakkında Yönetmelik) apply whenever a consumer agrees to pay for a home in advance, in full or in instalments, before it is delivered. The protection does not depend on nationality: a Russian, Iraqi or British buyer acting for private purposes is a consumer like a Turkish one.

Two limits matter. The seller must be a professional — a developer or a company selling in the course of business; a resale between two private individuals is governed by the general Code of Obligations. And a buyer of several units as a business may not be treated as a consumer. In flat-for-land projects (kat karşılığı), check who the contracting seller is and whether the developer's guarantee covers your unit before you sign.

What types of off-plan contract are there, and which is safe?

Law No. 6502, Articles 40–41, and the Regulation, Article 6 — the core rules

A pre-paid housing sales contract must be made in writing, either with registration of title at the land registry or as a sale promise drawn up by a notary. A contract that does not meet this form is void; the seller, however, cannot rely on the form defect against the consumer.

No pre-paid housing sales contract may be concluded before a building permit has been obtained. No payment, deposit or promissory note may be requested from the consumer before a valid contract exists. The consumer must receive the pre-contract information form at least one day before signing.

Off-plan contract types compared
ContractLegal positionProtection
Transfer of title under a construction servitude (kat irtifakı)Unit registered in your name at the land registry before completionStrongest: you are the owner of the share tied to your unit
Sale promise drawn up by a notary (düzenleme şeklinde satış vaadi)Valid; the developer promises to transfer title laterStrong if annotated on the title deed
Sale promise where the notary only certified signaturesDoes not meet the form requirementWeak; litigation risk
Reservation form or private sales contract at the sales officeVoid as to form; payments before a valid contract are not allowedWeakest; recover your money and insist on a proper contract

Should I annotate the sale promise on the title deed?

Yes, always. A notarised sale promise can be annotated (şerh) in the land register under Article 1009 of the Civil Code and Article 26 of the Land Registry Law. The annotation makes your right effective against anyone who later acquires the property, and mortgages or attachments registered after it do not prevail over it. If no transfer takes place within 5 years, the land registry deletes the annotation of its own motion, so a long-delayed project needs attention before that point.

Without an annotation, a developer in difficulty can sell or mortgage "your" unit to someone else, and you are left with a money claim. With one, you can sue for cancellation of the later transfer and registration in your name, and ask the court for an interim injunction (HMK Art. 389) to block further transfers. Before signing, check whether the developer's land already carries a bank mortgage — a mortgage registered before your annotation keeps its priority.

What is the deadline for delivery?

Since 1 October 2022, delivery must take place within 48 months of the contract date at the latest; the earlier limit was 36 months. Delivery means registration of title in your name or, where the unit was already registered under a construction servitude, handing over a habitable unit as well. The contract may set a shorter date, and the agreed date is binding. A clause pushing delivery beyond 48 months, or allowing open-ended extensions at the developer's discretion, does not take away your statutory protection.

What can I do if the developer is late?

Delay is a breach of contract. Under the Turkish Code of Obligations No. 6098, the developer is in default once you send a formal notice (ihtarname) through a notary, or automatically if a fixed delivery date was agreed (Art. 117). You can then grant a reasonable extra period and, if delivery still does not happen, choose between three options (Art. 123–125):

  • Insist on delivery and claim delay damages. Courts often measure the loss by the rent you could have earned, or had to pay elsewhere, during the delay. A contractual penalty clause (cezai şart) may give a fixed daily or monthly amount.
  • Withdraw and claim a refund. You recover everything paid, with interest, plus damages for the loss caused by the failed contract. Under the Regulation, a buyer who withdraws because the developer is in breach owes no withdrawal compensation.
  • Keep the contract but claim damages instead of delivery, for example the difference between the agreed price and today's market value of a comparable unit.

Which option is best depends on the stage of construction, the developer's solvency and market prices. A building that is 80% complete with a solvent developer is usually worth pursuing; a stalled site with no completion guarantee may call for withdrawal and a quick attachment of assets. Developers sometimes demand extra payments citing inflation and building costs. A one-sided price-increase clause can be challenged as an unfair term (Law No. 6502, Art. 5), and an argument of excessive hardship under Article 138 of the Code of Obligations is applied narrowly by the courts; it does not let the developer raise the price on its own.

  1. Collect the documents: contract, annotation, payment receipts, building permit, sales brochure and correspondence about the delay.
  2. Check the land registry: annotation in your favour, mortgages, attachments, concordat or bankruptcy notes.
  3. Check the guarantee: insurance policy, bank guarantee letter or escrow arrangement, and how to claim under it.
  4. Send a formal notice through a notary, setting an extra period and reserving all rights.
  5. Choose your remedy: delivery plus damages, withdrawal and refund, or damages instead of performance.
  6. Secure the claim: mediation for money claims, an injunction on the title, and an attachment where the developer is moving assets.

Important: Do not stop paying instalments without legal advice. Withholding payments without a properly documented breach can put you in default, and late-payment interest under the contract may then run against you — although the Regulation caps it at no more than 30% above the contractual rate.

What withdrawal rights do I have?

Separate from the remedies for breach, the law gives two withdrawal rights:

  • 14-day withdrawal (cayma, Law No. 6502 Art. 43; Regulation Art. 8): within 14 days of the contract, without giving reasons and without any penalty. A notice through a notary is enough, and the developer must refund within 14 days.
  • Withdrawal within 24 months (dönme, Art. 45; Regulation Art. 9): without giving reasons, subject to capped compensation. Taxes and fees come on top, notice is given through a notary and the refund is due within 180 days.
Maximum compensation for withdrawal within 24 months
Withdrawal withinMaximum compensation
First 3 months2% of the price
3 to 6 months4%
6 to 12 months6%
12 to 24 months8%
Developer in breach, death or permanent loss of earning capacity, unit sold to more than one buyerNothing

If the developer changes the project in a way you do not accept, you may withdraw free of charge within 1 month (Regulation Art. 11). The flat "2%" figure still quoted on some websites dates from before the 2017 amendment.

What protects me if the developer goes bankrupt or applies for concordat?

Before sales start, the developer of a project with 30 or more units must take out building completion insurance (yapı tamamlama sigortası) or provide another guarantee: a bank guarantee letter, a progress-payment escrow arrangement or a linked loan (Law No. 6502, Art. 42; Regulation Art. 12–16). Insurance proceeds do not fall into the developer's insolvency estate and cannot be attached by its creditors. Ask to see the policy or guarantee and confirm that your unit is covered.

A concordat (konkordato) or bankruptcy does not by itself extinguish your contract. A unit already validly transferred to you generally stays outside the estate; an annotated sale promise protects you against later owners and later attachments; other buyers are left with claims that must be filed in time with the commissioner or the bankruptcy office. During a concordat moratorium, new enforcement against the developer is suspended — see our guide on debt collection in Turkey for how concordat works.

Where and how do I bring a claim?

Off-plan disputes: where they go
ClaimForumMediation first?
Money claim below TRY 186,000 (2026)Consumer arbitration committee (tüketici hakem heyeti)No
Money claim above that, e.g. refund or delay damagesConsumer court (tüketici mahkemesi)Yes, mandatory (Law No. 6502, Art. 73/A)
Registration of title in your nameConsumer courtNo
Injunction to block transfer of the unitConsumer courtNo

If the facts suggest that the "developer" never intended to build, or deliberately sold the same unit to several buyers, a criminal complaint for fraud (Turkish Penal Code, Art. 157–158) may run alongside the civil claim. You do not need to travel: a lawyer can file under a power of attorney, which for court work can be signed at a Turkish consulate or before a local notary with an apostille and sworn translation; for land registry transactions, a consular power of attorney is the safe choice.

Can I get Turkish citizenship with an off-plan property?

Yes. Units under a construction servitude qualify, provided the appraisal, the declared price and the documented bank payments each reach USD 400,000 and the title carries a 3-year no-sale annotation. Where a notarised sale promise is used, it must cover the whole amount in one contract, with the full price paid upfront; separate promises cannot be combined. A stalled project therefore exposes both your money and your citizenship file. See our guides on Turkish citizenship by investment and citizenship by investment scams.

What should I check before signing?

  • Building permit (yapı ruhsatı) from the municipality, covering your block and unit.
  • Land registry record: owner of the land, mortgages, attachments and existing annotations.
  • Developer company: trade registry record, history, and any concordat or bankruptcy announcement.
  • Guarantee: completion insurance or alternative guarantee, with the policy number.
  • Contract: drawn up by a notary, delivery date within 48 months, specifications annex, penalty for delay, no unilateral price-increase clause.
  • Payments: only after the contract, by bank transfer to the developer's company account, never in cash or to an individual's account.
  • Annotation: registered on the title deed on the day of signing.

For completed properties, see our guide on buying property in Turkey as a foreigner. Note also that the land registry's secure payment system (Güvenli Ödeme Sistemi) is scheduled to become mandatory for property sales paid in cash or by transfer on 1 December 2026, after two postponements.

Common mistakes and red flags

  • Paying a "reservation fee" before a notarised contract exists.
  • Signing before the building permit has been issued.
  • Accepting a signature-certified promise instead of one drawn up by the notary.
  • Never annotating the promise on the title deed.
  • Missing the 14-day withdrawal window while still negotiating.
  • Agreeing to extra payments for "inflation" without legal review.
  • Waiting for years without a formal notice while the developer's finances deteriorate.

How LimanLegal can help

LimanLegal Law Firm reviews off-plan contracts before you sign, checks the building permit, land register, developer and guarantee, and makes sure your sale promise is properly drawn up and annotated. When a project is late, we send formal notices, negotiate with the developer, represent you in mediation and before consumer courts, claim under completion insurance or guarantees, and follow developers through concordat or bankruptcy. Most of this work can be done while you are abroad, under a power of attorney.

LimanLegal Law Firm is an Istanbul law firm advising foreign clients on Turkish law. We provide our services in English, Arabic, Russian, German, French and Turkish — write to us in English or in whichever of these languages you prefer.

  • WhatsApp: +90 540 097 1035
  • E-mail: [email protected]
  • Phone: +90 540 097 1035 (Mon–Fri 09:00–18:00, Istanbul time, UTC+3)
  • Address: Hukukçular Towers, Mustafa Kemal Paşa Caddesi, Cevizli, Seyitgazi Sokağı No:66/A, D:15, 34865 Kartal/İstanbul, Türkiye

Off-plan project late or in trouble?

Send us your contract, payment receipts, the title deed or annotation and any messages from the developer. We will tell you where you stand, which remedy fits your project and how to secure your money or your unit.

Contact us

FAQ

What is the maximum delivery period for off-plan property in Turkey?

For pre-paid housing sales by a developer to a consumer, delivery must take place within at most 48 months of the contract date (Pre-paid Housing Sales Regulation, Article 10, in force since 1 October 2022). Delivery means registration of title, or, under a construction servitude, registration plus handing over a habitable unit. The contract may set a shorter period.

Can I cancel an off-plan property purchase in Turkey?

Yes. You have 14 days from the contract to withdraw without giving reasons or paying any penalty. After that, you may still withdraw within 24 months without giving reasons, but the developer may claim capped compensation of 2%, 4%, 6% or 8% of the price depending on timing; nothing is owed if the developer is in breach, if the buyer dies or loses earning capacity, or if the unit was sold to more than one buyer.

What can I do if a Turkish developer delays delivery?

Put the developer in default with a formal notice through a notary, unless a fixed delivery date was agreed. You can then insist on delivery and claim damages for the delay, or withdraw from the contract and claim a refund of everything paid with interest and damages. Mandatory mediation applies before a consumer court claim for money, but not to a claim for registration of title.

Is a reservation agreement for off-plan property valid in Turkey?

For pre-paid housing sales, the contract must be either a title registration at the land registry or a sale promise drawn up by a notary; otherwise it is void as to form, although the developer cannot rely on that defect against the consumer. The developer also may not take a deposit or promissory note before a valid contract exists, and may not sign any contract before obtaining a building permit.

What happens to my off-plan apartment if the developer goes bankrupt in Turkey?

Bankruptcy or concordat does not by itself extinguish your contractual rights. A unit already validly registered in your name generally stays out of the developer's estate, and an annotated notarised sale promise is effective against later owners and later attachments. For projects of 30 units or more, the developer must have building completion insurance or another guarantee; insurance proceeds do not fall into the insolvency estate.

Do foreigners get consumer protection when buying off-plan property in Turkey?

Generally yes. Law No. 6502 protects anyone buying for private, non-commercial purposes, whatever their nationality, provided the seller is a professional developer or seller. A buyer of several units for commercial purposes may not be treated as a consumer, and sales between private individuals fall outside these rules.

Where do I file a claim against a Turkish developer?

For money claims below TRY 186,000 in 2026, the consumer arbitration committee decides; above that, the consumer court. Mandatory mediation must be tried before a consumer court claim for money, such as a refund. Claims concerning ownership itself, such as registration of title, go directly to court.

Can I get Turkish citizenship with an off-plan apartment?

Yes, if the unit has a construction servitude (kat irtifakı) or condominium title and the investment reaches USD 400,000 with the 3-year no-sale annotation. Where a notarised sale promise is used, it must cover the whole amount in a single contract with the full price paid upfront; separate promises cannot be added together.

Important: this article reflects the rules as of 23 October 2026. The arbitration committee threshold changes every January, the secure payment system has already been postponed twice, and specific contract terms can change the analysis — have your documents reviewed before acting.


Sources / legal basis
— Consumer Protection Law No. 6502, Articles 5, 40–46 and 73/A — mevzuat.gov.tr
— Pre-paid Housing Sales Regulation (Official Gazette 27 November 2014, No. 29188; amended 11 March 2017 and 4 August 2022)
— Turkish Code of Obligations No. 6098, Articles 117, 123–125, 138, 146 and 179–182
— Turkish Civil Code No. 4721, Article 1009; Land Registry Law No. 2644, Article 26
— Code of Civil Procedure No. 6100, Article 389 (interim injunctions)
— Ministry of Trade communiqué on monetary limits for consumer arbitration committees (Official Gazette 23 December 2025) — ticaret.gov.tr
— Turkish Citizenship Law No. 5901, Article 12, and its Implementing Regulation, Article 20

This article is general information about Turkish law and is not legal advice for any specific case.

Written by

Lawyer, co-founder of LimanLegal

Istanbul Bar Association

Education: MEF University Faculty of Law; LL.M. in Public Law, MEF University

Read more

Lawyer, co-founder of LimanLegal

Istanbul Bar Association

Education: Istanbul University Faculty of Law; MA in Management, Boğaziçi University

Read more

Facing a similar situation?

Send us a short summary of your case and copies of your documents by WhatsApp or e-mail. We will tell you what can be done and how the process works.

Back to articles